Brightwater Wastewater Conveyance

You are here Home  > All Projects >  Brightwater Wastewater Conveyance
Item image

In response to rapid population growth in King and Snohomish counties, a new regional wastewater treatment plant was designed to treat an average of 36 million gallons of wastewater a day, impacting nearly 190,000 people.

King County selected a joint venture including MWH to provide final design services for the conveyance portion of the new treatment system. As managing partner of the joint venture, MWH has provided project management, subconsultant management, project controls, QA/QC management, tunnel and shaft design, pipeline and lining design, mechanical engineering, electrical and I&C design, CADD production management, and preparation of contract documents.

    Location: King County, Washington, United States
    Region: Americas
    Service Offering: Engineering & Design
    Market Sector: Water & Wastewater
    Status: In Progress

    This project consisted of five tunnel drives under four main construction contracts (East, Central, West, BT3C) each from 11,100 to 21,000 feet in length, that connect to the new wastewater treatment plant and convey treated effluent to Puget Sound for discharge. The tunnel system was constructed in soft ground, utilizing earth pressure balance (EPB) and mixed shield slurry pressurized-face tunnel boring machine (TBM) techniques, with external groundwater heads ranging up to 240 feet (7.2 bars). Ground conditions range from dense glacially consolidated soils to loose glacial outwash and alluvial soils at depths from 50 to over 400 feet.

    As a part of the tunneling work, five permanent and one temporary shaft structures were constructed, with depths ranging from 40 to 200 feet. The different final shaft structures are used for flow distribution, pump station foundation, tunnel access, and flow sampling and measurement. In addition to the tunnels, the Brightwater Conveyance Project also included approximately 5,700 feet of pipeline connecting the tunnel system to the existing interceptors. These pipelines included three microtunnels (approximately 2,400-, 3,300-, and 500-feet), 2,200 feet of open-cut pipeline, diversion and drop structures. Other facilities included odor control stations, chemical injection systems, and final site work to include park and public art designed to educate people about the importance of clean water.

    The treatment plant currently has the capacity to treat an average of 36 million gallons of wastewater per day (mgd). By 2040, treatment capacity will be expanded to 54 million mgd. These capacities are for average wet-weather flows (AWWF). The plant must also be able to accommodate peak hourly flows of 130 mgd at start-up and 170 mgd by 2040.

    Dating back to the early 2000’s, King County Department of Natural Resources and Parks, Wastewater Treatment Division determined that a new wastewater treatment system (treatment plant, conveyance system and outfall) was needed. In 2003, King County selected MWH and another joint venture firm to spearhead the design of this project. Construction started in 2006 with limited treatment plant start-up and operations that began in September 2011. The Brightwater Treatment System is currently under construction and scheduled for system operation in September 2012 and completion of wetland restoration and odor control facilities by 2014.

    Source: http://www.kingcounty.gov/

    • Final design services
    • Project management
    • Subconsultant management
    • Project controls
    • QA/QC management
    • Tunnel and shaft design
    • Pipeline and lining design
    • Mechanical engineering
    • Electrical and I&C design
    • CADD production management
    • Preparation of contract documents
    • Underground tunnel connection design
    • 13 miles of influent and effluent tunnels to serve the proposed Brightwater Treatment Plant, a new 36-mgd wastewater treatment plant (WWTP)
    • Large diameter (greater than 16-feet) tunnels
    • Deep shafts of various diameters
    • Softground underground connection at 320 foot depths utilizing ground freezing.
    • BT3C Tunnel Contract Contractor Jay-Dee/Frank Coluccio JV won 2011  contractor of the year award from International Tunnelling Association (ITA)

    Photos:




    Our address

    Address:
    King County, Washington, United States
    GPS:
    47.548034, -121.983603

    Comments are closed.